How to Install a Retaining Wall

Basic Retaining Wall Installation

The following guidelines are for the installation of a basic retaining wall where no special circumstances are present. If your wall design exceeds 36” in height; is retaining a sloped hill; is being constructed on a slope; or requires a tiered wall design or similar, please contact an RCP Block & Brick near you for additional information and construction guidelines for your specific project.

See Available Retaining Wall Styles


Questions Along the Way? Contact an RCP location near you... we can help!


Project Considerations:

System Components:

Retaining Walls are designed to hold up a surcharge of soil such as a sloping hill or raised planter box. All Retaining Walls share some common building components in their construction. Below is an overview of the different types of walls and these common components.


Step 1: Excavation & Leveling Pad

The leveling pad is the first piece in constructing a stable wall that will last for years. This is the foundation on which the weight of the wall will rest, and therefore a very important piece to consider when installing any landscape wall.

Excavate the Site

Remove all surface vegetation and debris. Do not use this material as backfill. After selecting the location and length of the wall, excavate a base trench to the designed width and depth. These measurements will vary depending on block style and wall design (Contact RCP Block & Brick for project specific measurements); but expect the depth to be approximately as deep as the height of one block unit plus 6 inches; and as wide as the width of one block unit plus 12 inches.

Install the Leveling Pad

Fill the prepared trench with a 6” base off granular fill. We recommend 3/4” Crushed Gravel. Do NOT use pea gravel. Thoroughly compact and level the gravel to create your leveling pad.

NOTE: If grade changes along base of the wall, create a stepped leveling pad as required. Always start wall at lowest elevation, working to highest.

Retaining Wall Leveling Pad Diagram

Leveling Pad for Sloping & Level Grade

Installing Leveling Pad

Compacting Leveling Pad


Step 2: Base Course & Drainage Pipe

The first course of block that you lay is known as the base course. It is paramount that this course is absolutely level both front to back and side to side. If your base course is just a fraction out of level, it will be quite noticeable once you get to your final course.

Installing Base Course:

The first course of block will be placed below final grade, meaning you will be burying all or part of the first course. Place the first course of block units end to end on the prepared leveling pad. Make sure each unit is absolutely level. Complete this first course before adding additional courses.

NOTE: On units that use a pin connection, the long groove (receiving channel) on the unit should be placed down and the pin holes should face up. On units that use a lip connection system, remove the lips from the first course of block units to help in leveling by holding unit firmly on ground and striking lip with hammer.

PRO TIP: For alignment of straight walls, use a string line aligned on the pin holes of applicable units or back of the block of lipped units.

Installing Drainage Pipe:

After the base course of block is installed, you will need to install perforated drainage pipe behind this first course of block. Water will flow down through the backfill material to the base of the retaining wall. The drainage pipe will be located here to move the water away from behind the wall. Water (hydrostatic pressure) is the leading cause of retaining wall failures.

Retaining Wall Leveling Pad Diagram

First Course Must Be Absolutely Level


Step 3: Backfill & Compaction

Adding proper backfill to your retaining wall is extremely important as this is a key element in helping divert water away from the back of the wall, eliminating hydrostatic pressure, the leading cause of retaining wall failure. RCP recommends using 3/4" Crushed Gravel.

Backfilling Your Retaining Wall:

NOTE: If using block that requires pin connection, insert pins prior to backfilling to prevent gravel from plugging pin holes (Description in Step 4).

The width of backfill area will vary depending on your specific project, but expect to fill 12 inches behind the back of installed block units. Using 3/4” Crushed Gravel, begin to backfill after each course or two, filling open spaces between units, and filling open cavities/cores with gravel. As you backfill each course, do so in 6” increments (lifts) and compact each lift before adding the next. Backfill and compact behind each course before installing additional courses.

NOTE: For compaction vibrating plate compactor or hand tamper is suggested. Do not use heavy ride-on compaction equipment within 3’ (1m) from back of wall. Do not use jumping or ramming type compaction.

Backfill Retaining Wall Courses

Backfill Each Course With Gravel


Step 4: Installing and Connecting Additional Courses

The next step will be to start adding additional courses. This is where your landscape wall will really begin to take shape. Continue alternating between steps 3 and 4 until your retaining wall has reached the desired height.

Additional Course Considerations:

  1. As you add each additional course, continue checking to make sure each new block unit remains level.
  2. Take care that the joints (spaces between block units) do not line up with those of the courses above or below. This is known as a “Running Bond” pattern and helps create a structurally sound wall.
    NOTE: At curves, course bonding will adjust sideways. If “Stack Bond” occurs (joints start to line up with courses above or below), you can try to remove the rear lip on lipped units; re-organize pieces on multi-pieced block styles; or cut units accordingly to get back to running bond.

Block Connections:

Each retaining wall block style will require a specific method of connecting each unit to the course below. As you add additional courses, you will utilize the connection method specific to the style of block you are using.

  • Pin-Connection System: (Country Manor, Verazzo 4-Face, California Chateau, Stoneface, & Compac III/Standard III Units)
    Place the connector pins into the pre-existing pin holes on the top of the units (Note: Use only one pin per set of holes: Middle pin hole for vertical alignment; other holes can be used for wall setback or projection of unit. Some removal of debris in the pin holes and channel may be necessary prior to placement). Use approximately 2 pins per block. In instances where the pin may not align with receiving channel of above block, the pin can be removed, and masonry adhesive can be used in its place. Pins will line up into the receiving channel on the bottom of the above block unit. If pin lines up with a core/cavity of the block above, it will secure when the cavity is filled and compacted with gravel.
  • Lipped Connection: (Legacy, Citadel, Ridgestone, & Garden Wall Units)
    Many of our retaining wall block styles are engineered with a lip-connection system. The lip on the bottom back edge of each block rests behind the back edge of the block layer below. No pins or masonry adhesive are needed.
  • Masonry Adhesive: (Semplice & Country Cottage Units)
    For block styles that do not use a pin-connection system or lip-connection system, secure courses with the use of masonry adhesive applied every other course.
Adding Additional Courses

Adding Additional Courses

Avoid Stack Bond When Stacking

Avoid "Stack Bond" (Joints Lining Up)


Step 5: Capping the Wall

The final step to finishing your wall project is the addition of a wall cap. There are a variety of caps to choose from that compliment each individual wall style. The addition of a cap adds a finished look to the final product.

Cleaning Wall and Installing Cap:

Once the wall has reached the desired height, clean off the last course of block in preparation for the cap or coping to finalize the wall. This can be accomplished by brushing with broom or hosing off. Once units are dry and clean, use construction adhesive for a mechanical bond. Cap may be flush or overhanging as required by aesthetics and design.

Finish wall with wall cap

Finish With Wall Cap


Questions Along the Way? Contact an RCP location near you... we can help!

(800) 794-4727 | EMAIL
Chula Vista . Encinitas . Escondido . Lemon Grove . Murrieta . Santee
RCP Facebook
RCP Instagram
RCP Pinterest
RCP Youtube Channel
RCP Houzz